|
Portugal Photovoltaic technology status and prospects Pedro Sassetti Paes, Labelec - EDP group |
home
> annual reports
> annual report
2004 > |
In 2004, there have been no major changes at the energy policy level. The framework
is based on the government Cabinet Resolution No. 63/2003, which defines three
main strategic axes:
The main legal and incentive framework related to PV is:
Other institutions, such as Public Research Laboratories (INETI -
National Institute for Engineering, Industry and Innovation), Energy Agencies (ADENE and regional agencies), utilities (EDP) and private research institutions (INESC Porto - Institute for Systems and Computers Engineering), are performing applied research and
implementing PV demonstration projects. Besides these institutions, associations such as SPES (National Solar Energy Society) and
APISOLAR (manufacturer and installer association) are also involved in dissemination activities.
[ Top ]
There has been no significant new government initiative in 2004 as far as PV is
concerned. The legislation promoting renewable electricity (IPP law) is already
quite favourable for grid-connection PV applications, with buy-back rates of about
0,32 EUR/kWh (installed power above 5 kWp) and ~0,54 EUR/kWp (installed power
up to 5 kWp), guaranteed for the lifetime of the plant, with automatic adjustments
based on the inflation rate. IPP must deliver all the generated power to the grid
and the utility is obliged to buy the whole power.
Financial incentives are available under the PRIME programme (2003-2006) - III EC Framework Programme. Grants are provided on the basis of energy and environmental value of the projects, up to 40 % of the total eligible cost, with a maximum grant of 150 kEUR per application.
Indirect market development incentives for renewables are also available and include: reduction of VAT rate from 19 % to 12 % on renewable equipment, custom duties exemption and income tax reductions (up to 700 EUR for solar equipment).
In spite of this particularly favourable framework, only a few grid-connected installations have been realized in 2004:
The first Portuguese building integrated project, at the Renewable Energy Department of INETI, was slightly delayed and is expected to be concluded early 2005. The 12 kWp grid-connected system, to be installed on the south vertical façade of the building, is part of a broader project - Solar Building XXI - which also includes the use of passive and active solar thermal and daylighting. The project is partly supported by the PRIME programme.
Another initiative from the utility side should also be stressed: Enernova, a renewable energy company within the EDP Group, is planning to implement its first medium size power plant (300 kWp) in Sines (Alentejo). The preliminary technical and economical studies were carried out in 2004, together with the site selection. The system will likely be installed and operational in 2005.
There has been no significant development concerning the announced world largest
centralized PV power plant (64 MWp), to be built at the municipality of Moura
(Alentejo). The complex negotiation process among the major stakeholders is
still underway. This involves the promoter (Amper Central Solar, S.A.), the
Moura municipality, BP Solar (which will do the turn-key installation and will
build a module assembly factory near Moura), the financial institutions (which
will provide the investment on a project finance basis) and the government's
Directorate General for Energy (feed-in tariff discussion).
Besides these initiatives, there is a clear sign of growing interest in PV from IPP promoters, considering the huge amount of requests for grid interconnection points (the first stage of the licensing process in order to get the installation permits) received by the Directorate General for Energy, the government agency which is managing this process. The overall power requested in 2004 totalled 5,28 MWp, for a total number of 471 PV systems, with the following distribution:
If all these systems were realized in 2005/2006, they would more than double the total current installed capacity in Portugal and lead to a considerable change in the share of on-grid applications when compared to off-grid applications, which still dominate the PV market. [ Top ]
Besides PV modules, there are two solar type and stationary battery manufacturers (Tudor and Autosil).
A dozen companies are supplying and installing PV modules and BOS
components imported from the EU, USA and Japan. A few of these
companies produce power electronics for stand-alone PV applications(low power charge regulators, ballasts, etc.).
[ Top ]
The major barriers to the widespread of PV, namely in the built environment, have been identified and the following measures still need to be adopted: