Australia
Photovoltaic technology status and prospects
Dr Muriel Watt, Centre for PV engineering, University of New South Wales
home > annual reports > annual report 2004 >

General Framework

Fig. 1 - Australian cell line (photo BP Solar). The use of photovoltaic power systems (PV) in Australia continues to grow moderately, with installed capacity increasing by 16,6 % (almost identical to the previous year) to reach a total installed capacity of 45 630 kW by the start of 2004. Although not the main focus of government support programmes, off-grid non-domestic applications continue to dominate Australia's cumulative installed capacity (about 57 % by 2004, which is one percentage point lower than the previous year and down from about 75 % in the mid 1990's), with an annual growth rate that decreased slightly during 2003 to 14,6 % (compared with 18,6 % in 2002, 12 % in 2001 and 4 % in 2000). Off-grid domestic applications have enjoyed strong growth over the last decade and continue to benefit from the government support programmes aimed at increasing the use of BIPV and replacing diesel use with renewables. These applications accounted for almost 30 % of the cumulative installed capacity by 2004, again slightly lower than the figures for the previous years. Total off-grid cumulative installed capacity accounts for close to 87 % of PV installed in Australia.

The amount of PV that was connected to the grid has doubled each year over the past two years and the grid-connected market segment now exceeds 13 % of the total installed capacity compared with less than 1 % about seven years ago. The national BIPV support programme (which initially commenced in 2000) and, to a lesser extent, the mandatory renewable energy target (MRET) for electricity retailers and major energy users (implemented in 2001 and recently reviewed), which are both discussed later in this report, are widely perceived as the key factors behind this market growth. The Australian PV Industry Roadmap, launched in August 2004, identifies enhanced feed-in tariffs (a measure not implemented in Australia to date, although similar to MRET) as an important component amongst a suite of measures for promoting grid-connected PV in Australia.

The Australian electricity industry continues to play a role in both remote area power supply and grid-connected PV, although the degree of interest varies between businesses. This interest lies with both the retailing and network businesses and is largely stimulated by issues of customer contestability, the operation of greenhouse gas reduction agreements or licence conditions in a number of states and, more recently, as a means of reducing peak demand on mini grids and for selected substations.

The public is generally supportive of PV and interested in its use - however, even with rebates, PV investments for grid-connected households and community applications are difficult to justify on economic grounds because of Australia's relatively low electricity tariffs.
[ Top ]


National Programme

Fig. 2 - Aerial view of Kings Canyon (photo Advanced Energy Systems). The Australian Government has initiated a number of measures over recent years to support renewable energy in general and, in some cases, PV in particular. These include:

In June 2004, an Energy White Paper “Securing Australia's Energy Future” was released by the Australian Government. It includes a number of new measures targeting renewables:

Fig. 4 - Solomon Islands 600T Sun Mill (photo Solar Energy Systems). State government policies also support PV market growth. For example, the New South Wales Government has set a state-wide benchmark of reducing greenhouse gas emissions. The parties who are required to meet targets for greenhouse gas emissions must reduce the average emissions of greenhouse gases from the electricity they supply or consume to the pre-set individual benchmark level (or they pay a penalty). To achieve the required reduction in greenhouse gas emissions, benchmark participants purchase and surrender certificates called NSW Greenhouse Abatement Certificates (NGACs) which may be created by any eligible measures which reduce the average greenhouse intensity of electricity generation. In theory, this includes grid-connected PV systems, though in practice the relatively low penalty (buy-out) favours already economic or nearly-economic demand-side measures.

A number of key agencies at both Federal (the Australian Greenhouse Office) and State (the NSW Sustainable Energy Authority) levels have been restructured and their functions absorbed within broader departments. The likely impacts of these changes are not clear at this time, though for the time being most PV-related programmes are continuing in line with existing plans.
[ Top ]


Research, development and demonstration

Fig. 5 - Technician Training in Sri Lanka (photo GSES). Australian Government annual funding for PV R&D, D (including market incentives) was about 29,2 million Australian dollars during 2003 (compared with 20,3, 16,7 and 24,6 million Australian dollars for the three previous years). Funding from the state governments for the same period was around 0,9 million Australian dollars, significantly more than for the previous year.

Other PV research undertaken at Australian universities include:

[ Top ]


Implementation

Annual PV installations in Australia rose to 6,5 MW in the year up to the beginning of 2004 (up from 5,5 MW the previous year) and the figures for total installed capacity continue to be dominated by the off-grid market for agricultural/industrial uses (particularly telecommunications systems, shipping, rail and road signalling, water pumping, cathodic protection, billboards and electric fences) and private dwellings.

More than 3 MW in over 2 000 household / community building PV systems have been connected to the grid as a result of five years of operation of the PVRP. The programme has also resulted in about 3,5 MW and over 3 500 off-grid installations during the same period. This programme is scheduled to end in mid 2005, although extensions are being considered.

Fig. 6 - Telstra installation (photo BP Solar). The off-grid market is also helped by the RRPGP sub-programmes, with funding available for possibly a further five years. Although it is not PV specific, 2,13 MW of PV has been installed in small projects and 280 kW in larger mini-grid systems under this programme to end 2003. Almost all small systems include some PV and PV makes up about 90 % of installed capacity in small systems. Major PV projects supported by the RRPGP include a 55 kW system at an indigenous community and a 222 kW system at a tourist resort. Three concentrator dish PV systems, with a total capacity of 720 kW are under construction for indigenous communities in the Northern Territory. However, a recent government decision to remove diesel excise for stationary applications is likely to significantly affect the economics for diesel-replacement, which is a key driver for off-grid PV investments.

Green Power sales from the twelve Green Power retailers were recorded at about 131 GWh (year to date) in the third quarter of 2004 (a similar level to the previous year). While the Green Power market in its early stages was a strong driver for PV projects, PV electricity now accounts for less than 0,12 % of total green electricity purchased by the retailers - and is becoming relatively less significant each year. Only one third of the available Green Power products contain PV, with energy retailer EnergyAustralia's PureEnergy product accounting for about half of the Green Power PV electricity sourced nationally.

As for Green Power, the generic market based approach to renewable energy implementation under the MRET scheme has done little to stimulate the PV market. In 2003 about 0,15 % of renewable energy certificates (each equivalent to 1 MWh of generation) created under MRET were generated from PV systems. The modifications to PV deeming provisions mentioned earlier may increase interest in PV for MRET.

Although maintaining a general interest in PV, only a small number of electricity businesses are currently installing PV systems. Some retailers own and operate systems installed during the 1990's. There is some electricity business interest in using PV to achieve peak load reduction in diesel power stations. Electricity businesses will be involved with the four Solar Cities trials.
[ Top ]


Industry status

There are several Australian manufacturers of inverters, controllers, batteries and other components, as well as of specialized end use products, such as water pumps, electric fences, lights and hybrid power supplies. The inverters and controllers cover both grid and off-grid markets, several new products have been introduced and prices fell markedly in 2003, after being relatively stable for some years. This will have significant positive impacts on the overall cost of PV systems.
[ Top ]


Market development

Fig. 7 - Train signalling in the Australian countryside (photo BCSE). Growth in the local Australian market saw annual sales expanding by 17 % during 2003, down from the 27 % growth experienced the previous year. Imported cells, modules and BOS components are increasingly being used in the Australian market.

Australia's vast size and sparse population have made effective remote area telecommunications, power supplies, water pumping, navigation aids and transport route signaling critical and expensive. PV continues to provide an important commercial alternative to diesel and central grid supplies for such applications. The telecommunications market sector is likely to remain strong over coming years. The water pumping market is also performing strongly. Increased interest and activity are also evident in the medium sized centralised system market for supply to “mini-grids” for off-grid communities and commercial enterprises. Installations include flat plate and concentrator systems for aboriginal communities and for tourist facilities. The off-grid diesel replacement market for PV will however be adversely effected by a Government decision to remove fuel excise from off road diesel usage by 2012.

With its relatively low electricity tariffs, PV remains an expensive option for grid applications in Australia and with government grants for grid-connected systems scheduled to cease during 2005, there is a strong concern that this market sector may well stall.

The MRET review noted that further consideration should be given to special assistance measures that would support the development of the PV industry in Australia, including measures to support increased installation of systems. The PV Industry Roadmap, developed by the Australian Business Council for Sustainable Energy, has outlined a two part policy framework to drive investment in PV and Australian production. Firstly there are the broad-based industry and market development initiatives - market stimulation and support, removal of regulatory barriers and stimulation of industry capacity and capability. Secondly are measures focusing on specific PV markets - 150 000 grid-connected roof-top programme (underpinned by feed-in tariffs), diesel fuel replacement programme and export market initiatives. Targets for installed PV capacity of 350 MW and 6 740 MW by 2010 and 2020 respectively have been identified.
[ Top ]


Future outlook

Fig. 8 - Water pumping for stock (photo Solar Sales). The Australian PV Industry Roadmap suggests that PV in Australia is at a crossroads. The mid-term outlook for PV applications remains reasonably healthy, but the near-term may present challenges, especially for grid-connected applications. Green Power schemes and MRET are not delivering their initially anticipated levels of investment in PV. There continues to be a lack of PV installations for grid support or other distributed system benefits and it remains a challenge in Australia to promote the real value of distributed generation sources such as PV through appropriate regulation and market mechanisms. Recent state government building energy standards, such as the NSW BASIX scheme which gives credit to PV, may assist in the development of the BiPV market. In addition, consistent planning processes and guidelines, which typically operate at local government level, are needed in order to streamline building approvals and to guarantee solar access. Nevertheless, the installation of PV systems up to 10 kW is becoming more of a straightforward and accepted practice in Australia and work has been carried out on uniform installation and connection guidelines, and straightforward contracts. Interest and initiatives are in evidence at all levels in the community, but public funding support remains critical for the forseeable future.
[ Top ]


Further reading about Australia


[ Top ]