Task 5 Status Report
Grid interconnection of building integrated and other dispersed PV systems
home > annual reports > annual report 2003 >

Overall objective

The objective of Task 5 was to develop and verify technical requirements, which served as the technical guidelines for grid interconnection with building-integrated and other dispersed PV systems. The development of these technical requirements included safety and reliable linkage to the electric grid at the lowest possible cost. The systems to be considered were those connected with a low-voltage grid, which was typically of a size between one and fifty peak kilowatts.
[ Top ]


Means

Participants carried out five subtasks; Subtasks 10, 20, 30, 40 and 50 in order to achieve these objectives. The objectives of each subtask were as follows:

[ Top ]


Overview of past activities

[ Top ]


Summary of Task 5 - Subtask 50: Conclusions

Task 5 was officially concluded in 2003. The main outcomes of Subtask 50 activities are described below:

In conclusion, IEA PVPS Task 5 has performed important studies on topics related to grid interconnected PV systems. The reports published by Task 5 will serve as valuable information dissemination tools for utility people, PV industries, standard making bodies and customers. These reports will aid in them in understanding the problems and finding solutions for grid interconnection of PV systems. One example is that the grid interconnection guideline or standard of participating countries has been improved to distinguish the PV systems or inverter interface generation systems from rotating generators since the difference of protection requirements has been learned. Although there are differences of grid conditions by countries, requirements for the protection of grid connection for PV systems fall into almost the same concept. One of the most important points that Task 5 showed was that the probability of islanding is very small and costly protection systems for preventing islanding are not needed any more.

At the end of Task 5, the need for wider research in grid connection issues including all kinds of distributed generation systems in one distribution network was recognized. Similar to the way PV systems can be influenced by the presence of other types of generators, future distribution systems are expected to encounter analogue situations. While the international collaboration within Task 5 has contributed strongly to the understanding of such situations for PV power systems, in future, such issues are best dealt with as a cross-cutting issue for international cooperation between different energy technologies
[ Top ]


Industry involvement

Activities of Task 5 were conducted in the cooperation with well-balanced members from utilities or electric industries groups, national research groups, PV specialists and inverter manufacturers groups. [ Top ]


Reports produced in 2003

The following report was published in 2003. A CD-ROM including all the reports was published for the distribution. [ Top ]


Contact information

For information, contact the former Task 5 Chairman: Former participants and experts supporting them are listed in Task 5 participants.
All Task 5 reports are available for download from this website, publications' section. [ Top ]