Task 5 Status Report
Grid interconnection of building integrated and other dispersed PV systems
home > annual reports > annual report 2002 >
Last updated: 14 July 2003

Overall objective

The objective of Task 5 was to develop and verify technical requirements, which served as the technical guidelines for grid inter-connection with building-integrated and other dispersed PV systems. The development of these technical requirements included safety and reliable linkage to the electric grid at the lowest possible cost. The systems to be considered were those connected with a low-voltage grid, which were typically of a size between one and fifty peak kilowatts.
[ Top ]


Means

Participants carried out five subtasks; Subtasks 10, 20, 30, 40 and 50 in order to achieve these objectives. The objectives of each subtask were as follows:

[ Top ]


Utility aspects of grid-connected photovoltaic power systems

Overview of past activities

[ Top ]


Overview of 2002 activities

The main activities of Task 5 were completed with the Final Task Meeting and two-day Workshop held in Arnhem, The Netherlands, in January 2002. In the workshop, Task 5 findings for the Subtask 50 activities including islanding detection methods, probability of islanding and risk analysis for islanding were presented and discussed on the first day. On the second day, PV related guidelines and standards, inverter technology, the impact of PV penetration and the value of PV were presented and discussed. After the workshop, Task 5 participants carried out the preparation of PVPS Task 5 reports.
[ Top ]


Summary of Task 5 - Conclusions

The main outcomes of Subtask 50 activities are described below.

In conclusion, IEA  PVPS Task 5 has performed important studies on topics related to grid interconnected PV systems. The reports published by Task 5 will serve as valuable information dissemination tools for utility people, PV industries, standard making bodies and customers. These reports will aid in them in understanding the problems and finding solutions for grid interconnection of PV systems. One example is that the grid interconnection guideline or standard of participating countries has been improved to distinguish the PV systems or inverter interface generation systems from rotating generators since the difference of protection requirements has been learned. Although there are differences of grid conditions by countries, requirements for the protection of grid connection for PV systems fall into almost the same concept. One of the most important points that Task 5 showed was that the probability of islanding is very small and costly protection systems for preventing islanding are not needed any more.

Impacts of Power Penetration from PV into a Power System At the end of Task 5, the need for wider research in grid-connection issues including all kinds of distributed generation systems in one distribution network was recognized. Similar to the way PV systems can be influenced by the presence of other types of generators, future distribution systems are expected to encounter analogue situations. While the international collaboration within Task 5 has contributed strongly to the understanding of such situations for PV power systems, in the future, such issues are best dealt with as a cross-cutting issue for international cooperation between different energy technologies.
[ Top ]


Industry involvement

Activities of Task 5 were conducted in the cooperation with well-balanced members from utilities or electric industries groups, national research groups, PV specialists and inverter manufacturers groups.
[ Top ]


Key deliverables

The following reports were published in 2002. These reports can be downloaded from the publications' section:
[ Top ]


Task 5 participants

Current participants and experts supporting them are listed in Task 5 participants.
[ Top ]


Meeting schedule

[ Top ]